Preparation and Checks for Commissioning/Powering Up

Note the following when commissioning and switching on the Next Generation Hardware Appliance.

  • Make sure that the seal on the right-hand side of the Hardware Appliance is intact and has not been tampered with.

  • Make sure that the power supply units are seated correctly.

  • Connect both power cables.

  • Connect both network cables.

Both network cables must be plugged in and connected to the network before the Hardware Appliance is started.

  • Insert a battery into the External Battery Adapter and connect it.

The External Battery Adapter should already be equipped with a battery and operational even the Hardware Appliance is not installed immediately upon delivery.

Important!
It is important that the External Battery Adapter is constantly in use.

  • Connect the PIN Pad smart card reader to the Hardware Appliance.

  • Switch on the device to start booting. Booting will take about 5 minutes.

IP address

  • To set the IP Address follow, the instructions on the display on front of the device. See Getting Started for more information.